Skip to main content
D24

Templeville Light Segregation Scheme

Templeville Light Segregation Scheme

Templeville Light Segregation Scheme

Phase-7

The Contractor, SIAC  BP, have started their works on Templeville Road Cycle Route. The Scheme will be split up into 4 phases and they are as follows:

  1. Phase 1 - Wainsfort Road Roundabout to Glendown Road Southside 02/08/2022 – 19/08/2022
  2. Phase 2 – Wainsfort Road Roundabout to Glendown Road Northside 19/08/2022 – 15/09/2022
  3. Phase 3 - Glendown Road to Limekiln Lane Southside - update to follow for 2024
  4. Phase 4 – Glendown Road to Limekiln Lane Northside - update to follow for 2024

The decision to proceed with this scheme was taken on 3rd November 2022 and recorded on the SDCC Chief Executive Order system.

Copies of this decision are available on request from activetravel@SDUBLINCOCO.ie

Public Consultation commenced 07/03/2022 and ended 05/04/2022.

Templeville Road Cycle Scheme | South Dublin County Council's Online Consultation Portal (sdublincoco.ie)