Dodder Greenway Phases 4 - 6
Dodder Greenway Section 4 cycle route from Springfield Avenue to Lower Dodder Road.
Project Status - Traffic management to Springfield section is in place with works well under way. Phase 1 which includes crossing to Fairways/ Springfield Ave now complete.
Dodder Greenway Section 5 Firhouse Road/Butterfield Road
Project Status: Commencement of works is anticipated for May/June of 2024 on Section 5 of the Dodder Greenway from Firhouse Avenue to Butterfield Avenue.
Dodder Greenway Firhouse Road/Butterfield Road Part 8 Consultation commenced 06/07/2022 and ended 31/08/2022.
You can still view the details of the Part 8 Consultation here. The works will consist of the following, which will expand the fantastic Dodder Greenway Route further:
- Construction of a combination of single way and two-way cycle tracks adjacent to the vehicle carriageway
- Junction amendments to provide safer movement of pedestrians and cyclists
- Associated services
- Minor landscaping works
Dodder Greenway Section 6 On road section from Kiltipper Road to Old Bawn Road.
Project Status- Designs and options for route been considered approx 8 months to completion.